Building Inspections

 

What You Need To Know About The City of Reedley's Building Inspections

Inspection request can be made by fax at 559-637-2139 or phone 24-hours a day by calling the Building Inspection Line at 559-637-4200, EXT 112. To schedule an inspection you must call or fax your request before 9:00 a.m. on the day you are requesting the inspection. Inspection requests made after 9:00 a.m. will be scheduled for the following day. The objective is to provide all inspections within 16 hours of request.

 

The Building Official may be reached in the office Monday through Friday between 8:00 a.m. to 5:00 p.m. to answer questions, discuss problems or to arrange for special inspections.

The general contractor/owner-builder or his duly authorized representative is responsible for verifying that all work is complete prior to requesting an inspection. Re-inspections will be made as requested after all corrections have been made. A re-inspection fee may be charged if an inspection is rejected and the job is not complete or ready for inspection when requested.

For all inspections the approved plans must be on the job site and the Permit Job Card must be posted in a conspicuous place at the job site.

What is an inspection?

A building Inspection is a process in which a trained professional checks footings, foundations, plumbing, electrical, mechanical, structural frame, insulation, lath, and drywall, etc., to ensure they meet City ordinances and State building codes. Through this process, the City also ensures that new and remodeled buildings are constructed according to plans approved by the Community Development Department, and that buildings meet all health and safety regulations.

On-site inspections:

A city inspector will make inspections of a project while it is under construction, in order to ensure that it will be in compliance with applicable codes and ordinances, and that it will be safe and sound upon completion.

 

When are inspections needed?

Inspections must be done at the specified stage of construction. Do not proceed to the next stage of construction until the project has passed inspection for the current stage. It will be your responsibility to schedule an inspection. Inspections are required at the following stages of construction:

 

1. Underground/Under Slab Plumbing, Electrical, and Mechanical

To be done after all pipes, conduits and ducts are in place and secured, but not before backfilling.

 

2. Footings/Foundations

To be done after trenches, footings, and pad openings are excavated and cleared of loose material or mud, forms and reinforcement are erected and secured in place, but not before concrete is poured.

 

3. Under Floor Inspection

To be done after floor framing is complete and all required plumbing and mechanical is installed as per plans.

 

4. Rough-in of all system, Floor Nailing and Framing Inspection

All rough-in plumbing, electrical, mechanical, gas piping, etc., must be installed and inspections made before covering any work.

 

5. Under Floor Insulation

To be done after all insulation are in place and secured and prior to installation of the floor sheathing. Substantially wet or soaked wood construction is not to be covered with vapor or moisture barriers unless adequate provision is made for through drying of the structure.

 

6. Concrete Slab

To be done after all under-slab or under-floor piping and other auxiliary equipment items are in place and protected from contact with concrete. Screed boards or string lines shall be furnished by the contractor or owner to facilitate inspection of the slab thickness. This inspection must be performed and approved before placement of concrete slab or floor sheathing.

 

7. Roof Sheathing/Exterior Shear Inspection

To be done after all roof sheeting is in place and nailed as per the approved plans, but before any roofing materials are applied or loaded on the roof. Any required plywood planes on exterior walls, exterior connections and straps must also be nailed per the approved plans and inspected before being covered by exterior finish materials. The contractor is responsible for providing an approved ladder for safe roof access.

 

8. Masonry Fireplace Inspection

The following inspections must be called for during the construction of masonry fireplaces:

a. Footing (may be done during foundation inspection).
b. Throat (before chimney construction, after fire box construction).
c. Anchor Straps (at each plate line).
d. Bond Beam (before grouting of chimney).

The common practice of grouting as a fireplace chimney goes up is allowed only if arrangements have been made with the building inspector.

 

9. Complete Frame Inspection

To be done after all framing and roofing is complete (or material loaded and roof is substantially water tight). All rough plumbing, mechanical, and electrical installations must be in place. Water supply piping (hot and cold) shall be under pressure and all showers and/or tubes shall be filled with water. All drains, waste and vent piping shall be filled with water to 10 feet above the highest fitting or joint, or through the roof. The fireplace must be completed. Stucco lath or siding must be in place and nailed as per approved plans. Window frames and exterior door frames must be in place and properly flashed.

 

10. Insulation and Vapor Barrier

To be done after all insulation and moisture barriers are in place and secured, openings caulked and all required sealing done. Includes walls, floors and perimeter foundations, grounds covers, etc. Does not include loose insulation to be support by ceiling finish materials. Weather protections shall be provided before insulation. Wet or soaked insulation will be rejected. Substantially wet or soaked wood construction is not to be covered with moisture barriers unless adequate provisions is made for through drying of the structure.

 

11. Lath and Dry Wall

To be done on interior and exterior plaster system and all drywall applications after nailing (or other fastening system) is complete and before tape, plaster, or other coverings are applied. On multiple layer drywall (fire walls), each layer of drywall shall be separately inspected without exception. To be approved before scratch-coat is applied and before any drywall mud is applied.

 

12. Sewer Connection and Water Service from Shut-off to House

To be made after trenches are dug, piping in place and the appropriate test is applied. The contractor is responsible for supplying the inspector with an accurate as-built drawing showing locations of lines. This inspection must be done before any pipe is covered or trenches back-filled.

 

13. Gas Line Air Test

To be made after drywall is in place and brown-coat plaster and/or exterior siding is in place. Test requires the entire gas line to be capped off and a pressure of 10 p.s.i. be pumped into the line by the contractor. This pressure must hold for a minimum of 15 minutes.

 

14. Final Inspection

To be made when the structure is ready for occupancy. This shall include proper lot drainage, address posted, all plumbing fixtures connected and operable, all electrical fixtures and devices in place and electrically connected, insulation certificate posted, structure clean of debris or stored materials, thermal mass area (if any) installed as per approved plans, walls finishes complete as per approved plans, etc.

 

Other Inspections:
Other inspections may be required on particular jobs. These will be indicated on the approved plans and specifications, or the permit holder will be told of the by the Building Inspector.

 

Special Inspection:
When special inspections are specified on any particular project, in accordance with Section 306 of the Administrative Part of the Building Code, a qualified and approved special inspector is to be at the job site whenever work requiring special inspection is in progress. Such special inspector shall be pre-approved and registered with the Building Division of the City of Readily before inspections commence.

The new building cannot be occupied until a Certificate of Occupancy has been issued by the Building Official. This is normally issued after the project has passed a final inspection from the building inspector and cleared (in writing) from all other divisions (Planning, Public Works, Engineering, Fire Department, Community Services) within the City of Reedley.

 

After the project has been completed and has received final inspection, the building permit will be kept on file in the Building Division of the Community Development Department as evidence that the work has been completed according to appropriate codes and regulations.

 

 

 

 

©City of Reedley 2006